Integrated Road, Water and Sewer - Churchill Avenue
Federal contribution
$2.3M
$2,273,773
Federal share30%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jan 15, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Mar 1, 2010