Integrated Road, Water and Sewer - Pinewood Crescent

Ottawa, Ontario

completeWastewaterISF
Federal contribution
$963,763
Federal share32%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
May 19, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31981 in the federal list. How to read these figures.