Integrated Road, Water and Sewer - Pleasant Park Road
Federal contribution
$1.5M
$1,467,765
Federal share33%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 28, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start8 months earlyforecast Jun 1, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31982 in the federal list. How to read these figures.