Integrated Road, Water and Sewer - Stormont Street/Apeldoorn Avenue

Ottawa, Ontario

completeWastewaterISF
Federal contribution
$907,081
Federal share26%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Sep 4, 2009(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 14, 2011