Reconstruction of Cascade Street

Parry Sound, Ontario

completeDrinking WaterISF
Federal contribution
$933,333
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Parry Sound
Construction start
Sep 1, 2010(actual)
Construction end
Dec 3, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011

Also in Parry Sound

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32001 in the federal list. How to read these figures.