Integrated Road, Water and Sewer - Tweedsmuir Avenue
Federal contribution
$2.0M
$1,998,231
Federal share33%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Apr 26, 2010(actual)
- Construction end
- Sep 16, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2010
- Construction end2 weeks earlyforecast Sep 30, 2011
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32025 in the federal list. How to read these figures.