Back to projects

Library Building

Perth East, Ontario

completeCultureISF
Federal contribution
$345,879
Federal share29%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Perth East
Construction start
May 31, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2010
  • Construction end6 months earlyforecast Mar 31, 2011

Also in Perth East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32067 in the federal list. How to read these figures.