Knollcrest Lodge Fire Sprinkler & HVAC Upgrade

Perth East, Ontario

completeVentilationCVRIS
Federal contribution
$633,192
Federal share80%

of $791.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 7, 2021(actual)
Construction end
Dec 22, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2021
  • Construction end7 months lateforecast May 31, 2022