Rehabilitation of Milverton Wastewater Collection System

Perth East, Ontario

completeWastewaterCWWF
Federal contribution
$103,500
Federal share50%

of $207.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of East Perth
Construction start
Jul 4, 2017(actual)
Construction end
Aug 8, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2017
  • Construction end3 months earlyforecast Nov 1, 2017

Also in Perth East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48564 in the federal list. How to read these figures.