Finch-Roxborough Boundary Road Reconstruction
Federal contribution
$377,233
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Nov 26, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 25, 2009
- Construction end3 weeks earlyforecast Dec 15, 2010
Also in North Stormont
- New Well and Back-up Generators for the Township of North Stormont$365.0K
- Energy Efficiency for the Finch Community Arena$272.9K
- Settlement Area Sidewalks Improvements$80.0K
- Rehabilitation of Finch Bridge$75.9K
- Upgrading, Improvement and Rehabilitation of pumps #1 and #2, pump camera and mag meter at the Finch Water Treatment Facility$30.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32073 in the federal list. How to read these figures.