Energy Efficiency for the Finch Community Arena
Federal contribution
$272,941
Federal share80%
of $341.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- The Corporation of the Township of North Stormont
- Construction start
- Jan 15, 2023(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Jun 22, 2022
- Construction end2 months earlyforecast Sep 11, 2023
Also in North Stormont
- Finch-Roxborough Boundary Road Reconstruction$377.2K
- New Well and Back-up Generators for the Township of North Stormont$365.0K
- Settlement Area Sidewalks Improvements$80.0K
- Rehabilitation of Finch Bridge$75.9K
- Upgrading, Improvement and Rehabilitation of pumps #1 and #2, pump camera and mag meter at the Finch Water Treatment Facility$30.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63923 in the federal list. How to read these figures.