Settlement Area Sidewalks Improvements

North Stormont, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
2022
Built

Approved 2 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of North Stormont
Construction start
Aug 11, 2022(actual)
Construction end
Oct 26, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2022

Also in North Stormont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60959 in the federal list. How to read these figures.