Transitway Renewal - Nicholas Street Ramp
Federal contribution
$324,942
Federal share25%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32111 in the federal list. How to read these figures.