Transitway Renewal - Sackville Road Pedestrian Bridge
Federal contribution
$55,572
Federal share28%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Oct 29, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast May 3, 2010
- Construction end8 weeks lateforecast Aug 31, 2010