Baker Road Wastewater Treatment Plant Upgrade

Grimsby, Ontario

completeWastewaterISF
Federal contribution
$8.3M
$8,321,063
Federal share33%

of $25.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 19, 2009(actual)
Construction end
Oct 14, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 31, 2011