Schedule

Announced and approvedDec 21, 2009
201020112012
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
YMCA of Niagara
Construction start
Jan 4, 2010(actual)
Construction end
Feb 15, 2012(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Feb 1, 2010
  • Construction end4 months lateforecast Oct 31, 2011