Replacement of Main Street and Elm Street Watermains
Federal contribution
$1.1M
$1,050,000
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
today
2023202420252026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Grimsby
- Construction start
- Jul 1, 2025(actual)
- Construction end
- Oct 16, 2026(forecast)
Against the original forecast
- Construction start12 months earlyforecast Jun 22, 2026
Also in Grimsby
- Baker Road Wastewater Treatment Plant Upgrade$8.3M
- West Niagara YMCA$5.3M
- Grimsby Town Hall Redevelopment/Renovation$2.2M
- Water Main Rehabilitation 2021 - Upgrading of Cast Iron Water to PVC including Isolation Valves, Hydrants, and Service Connections$938.5K
- Water Main Rehabilitation 2019 - Upgrading of Cast Iron Water to PVC including Isolation Valves, Hydrants, and Service Connections$826.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62962 in the federal list. How to read these figures.