Westmount Recreation Centre
Federal contribution
$4.0M
$3,981,849
Federal share19%
of $21.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010201120122013
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Nov 23, 2012(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 31, 2010
- Construction end8 weeks lateforecast Oct 1, 2012