Westmount Recreation Centre

Hamilton, Ontario

completeRecreationISF
Federal contribution
$4.0M
$3,981,849
Federal share19%

of $21.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010201120122013
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Hamilton
Construction start
Oct 18, 2010(actual)
Construction end
Nov 23, 2012(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Aug 31, 2010
  • Construction end8 weeks lateforecast Oct 1, 2012

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32240 in the federal list. How to read these figures.