Sir Wilfrid Laurier Rehabilitation

Hamilton, Ontario

completeRecreationISF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Hamilton
Construction start
Mar 29, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 30, 2010