Ottawa Public Library - Cumberland Branch Retrofit
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jan 4, 2010(actual)
- Construction end
- Aug 12, 2010(actual)
Against the original forecast
- Construction end4 months lateforecast Apr 2, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32270 in the federal list. How to read these figures.