Morgan Firestone Arena Twinning

Hamilton, Ontario

completeSportISF
Federal contribution
$3.4M
$3,395,712
Federal share33%

of $10.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 25, 2009
ApprovedJan 4, 2010
20102011
Built

Approved 3 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Hamilton
Construction start
Aug 23, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011