Cobble Hills Road Rehabilitation
Federal contribution
$218,816
Federal share32%
of $690.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Zorra
- Construction start
- Jul 10, 2009(actual)
- Construction end
- Oct 1, 2009(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 1, 2009
Also in Zorra