County Road 6 Rehabilitation

Zorra, Ontario

completeHighways and RoadsISF
Federal contribution
$397,100
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Oxford
Construction start
Sep 14, 2009(actual)
Construction end
Oct 28, 2009(actual)

Against the original forecast

  • Construction end11 months earlyforecast Oct 1, 2010

Also in Zorra

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32440 in the federal list. How to read these figures.