Embro Matheson Park Revitalization
Federal contribution
$93,176
Federal share40%
of $232.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Zorra
- Construction start
- Oct 21, 2021(actual)
- Construction end
- Nov 22, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 5, 2021
- Construction end6 months lateforecast Jun 3, 2022
Also in Zorra
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57639 in the federal list. How to read these figures.