Earl Armstrong Road
Federal contribution
$11.2M
$11,223,194
Federal share33%
of $34.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Aug 28, 2009(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32359 in the federal list. How to read these figures.