Hazeldean Road Widening
Federal contribution
$21.4M
$21,421,000
Federal share33%
of $65.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2009
- Construction end2 weeks lateforecast Oct 14, 2011
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32372 in the federal list. How to read these figures.