Axminster Drive Reconstruction
Federal contribution
$254,772
Federal share15%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Richmond Hill
- Construction start
- Mar 8, 2010(actual)
- Construction end
- Jun 18, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Apr 12, 2010
- Construction end6 months earlyforecast Dec 15, 2010