Prince of Wales Drive Drainage Culvert

Ottawa, Ontario

completeHighways and RoadsISF
Federal contribution
$66,667
Federal share33%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Nov 2, 2009(actual)
Construction end
Nov 20, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2009
  • Construction end8 months earlyforecast Jul 31, 2010

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32393 in the federal list. How to read these figures.