Drummond Street West Corridor Rehabilitation
Federal contribution
$123,829
Federal share32%
of $390.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Perth
- Construction start
- Oct 8, 2009(actual)
- Construction end
- Aug 3, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 15, 2009
- Construction end8 weeks earlyforecast Sep 30, 2010
Also in Perth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32400 in the federal list. How to read these figures.