Improvements to Mer Bleue Road

Ottawa, Ontario

completeHighways and RoadsISF
Federal contribution
$981,860
Federal share22%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Sep 28, 2009(actual)
Construction end
Sep 24, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2009