Back to projects

Pedestrian Urban Multi-Use Pathways - Alta Vista Transportation Corridor Pathway

Ottawa, Ontario

completeActive TransportationISF
Federal contribution
$77,676
Federal share31%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Jul 12, 2010(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 28, 2010
  • Construction end4 weeks lateforecast Sep 30, 2010

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32434 in the federal list. How to read these figures.