Southwest Transitway Extension - Fallowfield to Barrhaven
Federal contribution
$13.5M
$13,471,871
Federal share28%
of $48.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 16, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2009
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32462 in the federal list. How to read these figures.