Pedestrian Urban Multi-Use Pathways - Sawmill Creek Pathway Connections

Ottawa, Ontario

completeActive TransportationISF
Federal contribution
$78,420
Federal share31%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Jul 12, 2010(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2010

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32476 in the federal list. How to read these figures.