completeHighways and RoadsISF
Federal contribution
$876,093
Federal share29%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
May 27, 2010(actual)
Construction end
Oct 25, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 1, 2010
  • Construction end3 weeks lateforecast Oct 3, 2011