New Sidewalks - Coventry

Ottawa, Ontario

completeHighways and RoadsISF
Federal contribution
$37,729
Federal share25%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Aug 17, 2009(actual)
Construction end
Nov 15, 2010(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2010
  • Construction end7 weeks lateforecast Sep 30, 2010

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32492 in the federal list. How to read these figures.