Pedestrian and Rural Pathways - Prescott Russell Pathway linkage

Ottawa, Ontario

completeHighways and RoadsISF
Federal contribution
$567,508
Federal share28%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Sep 2, 2010(actual)
Construction end
Sep 23, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 21, 2010
  • Construction end5 weeks earlyforecast Oct 31, 2011