New Sidewalks - Hunt Club - Billy Bishop
Federal contribution
$32,298
Federal share18%
of $180.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2010
- Construction end2 months lateforecast Sep 30, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32539 in the federal list. How to read these figures.