Municipal Office Renewal

Rainy River, Ontario

completeGreen EnergyISF
Federal contribution
$15,000
Federal share33%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Rainy River
Construction start
Jul 27, 2009(actual)
Construction end
Oct 15, 2009(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 31, 2009