completeRecreationISF
Federal contribution
$1.0M
$1,000,000
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Shelburne
Construction start
Mar 5, 2010(actual)
Construction end
Jan 31, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 1, 2009
  • Construction end7 weeks lateforecast Dec 15, 2010