Shelburne Wastewater Treatment Plant Upgrade
Federal contribution
$696,892
Federal share30%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2015
20162017
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Shelburne
- Construction start
- Aug 12, 2016(actual)
- Construction end
- Mar 31, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2016
- Construction end5 months lateforecast Nov 1, 2016
Also in Shelburne
- Well No. 3 Pumphouse Rehabilitation$1.9M
- Construction of a Water Treatment Facility and Installation of Water Meters$1.4M
- Upgrades to the Shelburne Community Centre$1.0M
- Centre Dufferin Recreation Complex Pitched Roof Replacement$284.6K
- Rehabilitation and Clean out of the Town of Shelburne Wastewater Storm Ponds$171.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46381 in the federal list. How to read these figures.