Rehabilitation and Clean out of the Town of Shelburne Wastewater Storm Ponds
Federal contribution
$171,130
Federal share28%
of $614.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Shelburne
- Construction start
- Nov 2, 2017(actual)
- Construction end
- Aug 9, 2019(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2017
- Construction end2 months lateforecast May 31, 2019
Also in Shelburne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52148 in the federal list. How to read these figures.