Rehabilitation and Clean out of the Town of Shelburne Wastewater Storm Ponds

Shelburne, Ontario

completeWastewaterCWWF
Federal contribution
$171,130
Federal share28%

of $614.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
20182019
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Shelburne
Construction start
Nov 2, 2017(actual)
Construction end
Aug 9, 2019(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2017
  • Construction end2 months lateforecast May 31, 2019