George Forster Historical House and Barn Restoration

Richmond Hill, Ontario

completeCultureISF
Federal contribution
$624,950
Federal share27%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Richmond Hill
Construction start
Dec 7, 2009(actual)
Construction end
Aug 6, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 17, 2009
  • Construction end7 months earlyforecast Feb 28, 2011