Major renovation of SP-2 wastewater pumping station
Federal contribution
$635,556
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2009
201020112012
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Matane
- Construction start
- Sep 17, 2009(actual)
- Construction end
- Mar 8, 2012(actual)
Against the original forecast
- Construction end21 months lateforecast Jun 15, 2010
Also in Matane
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32702 in the federal list. How to read these figures.