Water Systems Upgrades of part of the Saint-Joseph and Desjardins streets
Federal contribution
$968,000
Federal share40%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Matane
- Construction start
- Apr 25, 2022(actual)
- Construction end
- Sep 16, 2022(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 6, 2022
- Construction end6 weeks earlyforecast Oct 28, 2022
Also in Matane