Water Systems Upgrades

Matane, Quebec

completeWastewaterGIS
Federal contribution
$854,560
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Matane
Construction start
Aug 11, 2020(actual)
Construction end
Nov 26, 2021(actual)