Ronald McDonald House
Federal contribution
$2.7M
$2,672,521
Federal share21%
of $13.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
201020112012
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Kids' Care Oncology Central West Ontario
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction start8 months lateforecast Feb 28, 2010
- Construction end3 weeks lateforecast Mar 9, 2012
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32811 in the federal list. How to read these figures.