Pathways Community Therapeutic Pool and Recreation Facility Expansion

Sarnia, Ontario

completeRecreationISF
Federal contribution
$593,333
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Aug 9, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start11 months earlyforecast Jul 1, 2011