Centre of Excellence for Children and Families
Federal contribution
$2.0M
$2,000,000
Federal share33%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Lutherwood
- Construction start
- May 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2009
- Construction end2 weeks lateforecast Oct 17, 2011