Annie Williams Park Upgrades
Federal contribution
$500,197
Federal share82%
of $609.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2010
2010
Built
Approved 7 months before the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Town of Bracebridge
- Construction start
- Nov 30, 2009(actual)
- Construction end
- Jun 25, 2010(actual)