Port Sydney Beautification
Federal contribution
$250,009
Federal share100%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.4 years before the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Town of Huntsville
- Construction start
- Apr 30, 2009(actual)
- Construction end
- Jun 25, 2010(actual)
Also in Huntsville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33193 in the federal list. How to read these figures.